The impression of architecture inside the subway station
The ceiling of Ba Son underground station is designed with a beautiful wave shape, the basements are currently under construction and completing the architectural and electromechanical parts. In addition, the temporary landscape reconstruction above the station is also urgently completed by the end of April 2021.
Recently, the Urban Railway Management Board (MAUR) said that the cumulative volume of package CP 1b (the underground section from Opera House to Ba Son station) to now is estimated at 93.36%.
Currently, the completion work (architecture + electromechanical) of the underground floors below and the temporary landscape reconstruction work above Ba Son station such as lawns, surface sewers, roads, sidewalk … is being constructed urgently by the contractor.
According to MAUR, it is expected that by the end of April 2021, the reconstruction and completion of B1 floor will be basically completed.
Representatives of the Management Board of HCMC Urban Railways go to inspect the construction site at Ba Son underground station
Meanwhile, at the Opera House station area, MAUR is also planning to complete the re-establishment and dismantling of the barrier on Le Loi Street, from Nguyen Hue Street to Pasteur before April 30.
This helps to improve traffic conditions and return an open space as before to a bustling central area with business, sales and service activities.
To serve the construction of the Opera House underground station which is station 2 out of 14 stations of Metro Line 1, a large part of Le Loi street (from Dong Khoi street to Pasteur street) has been occupied. assigned to the construction barrier contractor in mid-2014.
Currently, the reconstruction work such as breaking temporary floors, cutting diaphragm walls, filling sand, drainage culverts … above Opera House Station (Le Loi Street, section from Nguyen Hue Street to Pasteur Street) is underway. construction urgently. At the same time, the underground floors below the station, the architectural and electromechanical work is still being completed by the contractor.
The Urban Railway Management Board will continue to coordinate and urge the construction contractor to strive to basically complete the package 1b (City Theater Station and Ba Son Station) by the end of May 2021.
At the Opera House station on Le Loi Street, the section from Nguyen Hue Street to Pasteur is under construction for reconstruction and the plan to remove the barrier above the station
The image is under construction to break the temporary floor, cut the diaphragm wall, and add sand above the Opera House station (Le Loi street, section from Nguyen Hue to Pasteur)
Workers are continuing to complete construction (architecture + electromechanical) for the underground floors below the Opera House Station
The escalator is under construction to move between the basements at the Opera House station
Cre to Doanh nghiệp và tiếp thị
エキサイティングなエンターテイメントとたくさんのエキサイティングなチャンスがあなたを待っている オンラインカジノ一覧 で最高のカジノゲームをプレイしましょう。あなたのゲームキャリアを成功と情熱でスタートさせるために、今すぐ参加して、寛大な新規プレイヤーボーナスを手に入れましょう!ご自宅でくつろぎながら、高品質のグラフィック、ライブディーラー、そして本物のカジノの雰囲気をお楽しみください!カジノは、人々が日常生活から離れ、興奮を楽しむことができる場所です。 しかし現在では、多くの人がオンラインカジノで同じ感動とアドレナリンを得ながら、自宅で時間を過ごすことを好むようになりました。