CONSTRUCTION PROGRESS OF BEN THANH CENTRAL STATION OF HCMC METRO LINE NO.1(BEN THANH – SUOI TIEN)
The build of the high and depot of the metro number of 1 (Ben Thanh – Suoi Tien route) in Ho Chi Minh City has entered the end of its phase.
– Pouring structural concrete reaches 83.7%
– Reinforcement reaches 88.0%
– Anti-removable frame system reaches 84.8%
– The architectural and electromechanical parts are expected to begin implementation after the Contractor hand over part of the B2 floor in advance (Section 1-12).
There are also other items that are actively being deployed such as the Entrance Gate, Ventilation Tower …
Total progress of CP1a package (Ben Thanh Station and Le Loi Open Tunnel) reached 80.74%
Currently, with 5 million safe man-hours and accelerated construction progress on the construction site to ensure SAFETY – QUALITY – EFFICIENCY, testosteron propionat the Urban Railway Management Board will continue to work with the contractor to In the end, the entire construction of CP1a package will be completed in 2021 according to the plan.