UPDATE ABOUT THE MARQ PROJECT IN OCTOBER 2019
JJLand would like to give you information about the status of current construction progress of The Marq project.
As of September 2019, the project’s construction is as follows:
- Basement: Prepare for wall paint and finishing. The goal is to hand over for M&E work in early November 2019.
- Structure: Completed bare-shell to the 5th floor, under construction formwork and iron for the 6th floor (Tower A) at the moment.
- Finishing work: Completed building of boundary walls on the 2th floor (Tower A) and preparing to build walls of apartments.
Photos of construction progress of The Marq project in October 2019:
The Marq project
🏢 Type: Apartment building
💎 Segment: Luxury
👨💼 Developer: HongKong Land & Hoa Lam
👨🏫 Architect: P&T Consultants, Arup Group, PTang Studio, Ecoplan Asia
👷♂️ Contractor: Coteccons
💰 Bank guarantee: Vietbank
🔑 Location: 29B Nguyen Dinh Chieu St., Da Kao Ward, District 1, HCMC
🔮 Total area site: 5,146 sqm
🏗 Construction density: 45%
🏬 No. of storeys: 26 storeys high & 4 -storey basement
🏘 No. of towers: 2
🏠 No. of units: 515
🤝 Handover standard: Fully furnished with high-class furniture
👌 Handover date: Quarter IV/2022 (expected)
📕 Tenure: freehold (Vietnamese), 50-year leasehold (foreigner)
For more information about the project, feel free to contact JJLand via:
☎️ +84 938 350 370
📬 contact@jjland.com.vn
All comments about JJLand, please send to:
📱 +84 908 350 370 (Mr. Jedi – CEO)
Thank you! 🥰